A power system consists of 2 areas (Area 1 and Area 2) connected by a single tie-line. It is required to carry out a load flow study on this system. While entering the network data, the tie-line data (connectively and parameters) is inadvertently left out. If the load flow program is run with this incomplete data.

A
The load flow will converge only if the slack bus is specified in area 1
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
The load flow will converge only if the slack bus is specified in area 2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
The load flow will converge only if the slack bus is specified in either area 1 or area 2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
The load flow will not converge if only one slack bus is specified.
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D The load flow will not converge if only one slack bus is specified.
For load flow study to converge there must be one slack bus in the system. As while entering the network data the tie-line data is not considered, two areas will now be treated as seperate areas hence two slack bus (one in each area) are required.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
LFC: Two Area Control
POWER SYSTEMS
Watch in App
Join BYJU'S Learning Program
CrossIcon