A pre-timed four phase signal has critical lane flow rate for the first three phases as 200, 187 and 210 veh/hr with saturation flow rate of 1800 veh/hr/lane. The lost time is given as 4 second for each phase. If the cycle length is 60 sec, the effective green time (in second) of the fourth phase is_____


  1. 15.755

Open in App
Solution

The correct option is A 15.755
y1=q1s1=2001800
y2=q2s2=1871800
y3=q3s3=2101800
y=y1+y2+y3+y4
=0.33167+y4
L=4×4=16sec
C0=1.5L+51y
60=1.5×16+510.33167y4
0.66833y4=1.5×16+560
y4=0.185
Eff. green time for 4th Phase
=(C0L)×y4y1+y2+y3+y4
=(6016)×0.1850.33167+0.185
=15.755sec

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Electromagnetic Spectrum
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon