A pre-timed three phase signal has critical lane flow rate for first two phases as
300,278 veh/hr with saturation flow rate as
1800veh/hr/land for all phases. The lost time is
5 seconds for each phase. If cycle length is
60 seconds, then the effective green time of the third phase is seconds.
- 18.35