A producer of Sun-Stop suntan lotion uses 400 gallons per week of a chemical which is ordered in EOQ quantities of 5,000 gallons at a quantity discount cost of Rs. 3.75 per gallon. The procurement lead time is 2 weeks, and a safety stock of 200 gallons is maintained. The storage cost is Rs.0.1 per gallon-week. The average inventory maintained is