CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A producer of Sun-Stop suntan lotion uses 400 gallons per week of a chemical which is ordered in EOQ quantities of 5,000 gallons at a quantity discount cost of Rs. 3.75 per gallon. The procurement lead time is 2 weeks, and a safety stock of 200 gallons is maintained. The storage cost is Rs.0.1 per gallon-week. The average inventory maintained is

A
5200 gallon
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2700 gallon
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
1000 gallon
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2500 gallon
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 2700 gallon
Maximum inventory:

Imax=Safety stock+EOQ

= 200 + 5,000 = 5,200 gallon

Average inventory,

Iavg=Imax+Imin2=5200+2002=2700 gallon

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Basic Terms of Accounting
ACCOUNTANCY
Watch in App
Join BYJU'S Learning Program
CrossIcon