A project consists of 4 activities with the following data :
Indirect cost = Rs.100/day.
The minimum cost project duration (days) is ____.
A
18
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
20
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
19
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
17
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B20 ActivityCost slope=Cc−NcNT−CTCrashingPossibilityA(220−100)9−7=602B−−C(320−200)/6−4=602D(450−300)/10−9=1501
Path––––––Duration–––––––––– A - D : 9 + 10 = 19 B - C - D : 6 + 6 + 10 = 22
Crashing Possibility : CriticalCost SlopeCrashingActivityprovisionB−Not PossibleC602 daysD1501 day
By crashing activity 'C' by 2 days.
'C' can be crashed because the crash cost per day is less than indirect cost/day. Hence the total cost will decrease
path–––––Duration––––––––––
A - D : 9 + 10 = 19
B - C - D : 6 + 4 + 10 = 20
Crashing Possibility at this stage : CriticalCost SlopeCrashingActivityproblemB−Not PossibleC60Not Possible(fully crashed)D150Not economical
Further crashing is possible but not economical because the crash cost per/day is greater than indirect cost per/day and the total cost will start increasing, Hence minimum cost project duration = 20 days.