A project consists of 4 activities with the following data :


Indirect cost = Rs.100/day.
The minimum cost project duration (days) is ____.

A
18
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
20
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
19
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
17
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 20
ActivityCost slope=CcNcNTCTCrashingPossibilityA(220100)97=602BC(320200)/64=602D(450300)/109=1501




Path–––– Duration––––––––
A - D : 9 + 10 = 19
B - C - D : 6 + 6 + 10 = 22

Crashing Possibility :
CriticalCost SlopeCrashingActivityprovisionBNot PossibleC602 daysD1501 day

By crashing activity 'C' by 2 days.
'C' can be crashed because the crash cost per day is less than indirect cost/day. Hence the total cost will decrease



path––– Duration––––––––
A - D : 9 + 10 = 19
B - C - D : 6 + 4 + 10 = 20

Crashing Possibility at this stage :
CriticalCost SlopeCrashingActivityproblemBNot PossibleC60Not Possible(fully crashed)D150Not economical

Further crashing is possible but not economical because the crash cost per/day is greater than indirect cost per/day and the total cost will start increasing, Hence minimum cost project duration = 20 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction and Total Cost of the Project
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon