Question
A project consists of 7 activities
Activity
Duration
(days)
Precedence
Relationship
A
5
A<C.D
B
7
B<E
C
10
C<G
D
16
D<F
E
3
E<F
F
9
F<G
G
7
-
The duration and precedence relationship are given in the table. The time to complete the activities along the critical path is ______
A
40
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
22
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
26
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
37
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is
D
37
(B)
Activity
Predecessor
A
-
B
-
C
A
D
A
E
B
F
D, E
G
C,F
Suggest Corrections
0
Similar questions
Q.
For a project plan activity duration and their relationship is given below:
Activity
Preceding Activity
Duration (days)
A
−
4
B
−
10
C
A
8
D
A
,
B
7
E
C
,
D
9
The duration of critical path is ____ days.
Q.
The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship "X < Y, Z" means that X is the predecessor of activities Y and Z. The time to complete the activities along the critical path is ____ weeks.
Activity
Duration (Weeks)
Precedence Relationship
A
5
A < B, C, D
B
7
B < E, F, G
C
10
C < I
D
6
D < G
E
3
E < H
F
9
F < I
G
7
G < I
H
4
H < I
I
2
....
Q.
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are
Activity
Predecessors
Duration (days)
a
-
2
b
-
4
c
a
2
d
b
3
e
c
2
f
c
4
g
d, e
5
Q.
The project activities, precedence relationships and durations are described in the table. The critical path of the project is
Activity
Precedence
Duration (in days)
P
-
3
Q
-
4
R
P
5
S
Q
5
T
R, S
7
U
R, S
5
V
T
2
W
U
10
Q.
A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
Activity
Immediate predecessor
Duration (days)
A
-
4
B
A
3
C
A
7
D
B
14
E
C
4
F
D, E
9
The minimum project completion time (in days) is
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Levels of Management
BUSINESS STUDIES
Watch in App
Explore more
Levels of Management
Standard XII Business Studies
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app