Question


A project consists of 7 activities. The network along with the time duration(in days) for various activities is shown in the figure. The number of Activities whose float is more than 1 day is

A
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
3
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
0
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 3
To determine the critical nodes and total float, above computations are shown in the table below.
Activity Time
(dij)
Earliest time Latest time Total float
(LjEi)dij
Ei Ei+dij Ljdij Lj
1-2 4 0 4 3 7 3
1-3 7 0 7 0 7 0
1-4 6 0 6 8 14 8
3-4 5 7 12 9 14 2
3-5 7 7 14 9 14 0
5-7 6 14 20 14 20 0
5-6 5 14 19 15 20 1

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Women’s Political Representation
CIVICS
Watch in App
Join BYJU'S Learning Program
CrossIcon