1
You visited us
1
times! Enjoying our articles?
Unlock Full Access!
Byju's Answer
Other
Other
Critical Path and Project Completion Time
A project con...
Question
A project consists of 7 activities with the following data.
Activity
Predecessor
Duration (days)
A
−
4
B
−
3
C
A
3
D
A
5
E
B
,
C
5
F
B
,
C
6
G
D
,
E
8
The minimum time required to complete the project (in days) is ____.
Open in App
Solution
Path
Duration (days)
A
−
D
−
G
4
+
5
+
8
=
17
A
−
C
−
E
−
G
4
+
3
+
5
+
8
=
20
(
C
P
)
B
−
E
−
G
3
+
5
+
8
=
16
B
−
F
3
+
6
=
9
A
−
C
−
F
4
+
3
+
6
=
13
Minimum time required to complete the project = 20 days.
Suggest Corrections
1
Similar questions
Q.
A project consists of 4 activities with the following data :
Indirect cost = Rs.100/day.
The minimum cost project duration (days) is ____.
Q.
Network is drawn using the following data: A and B are starting activities and takes 8 and 4 days respectively for completion. Activity C follows B, D follows A and C , D is the finishing activity . Activity C and D takes 10 and 6 days respectively for completion . The time required for completion of the project is ____
Q.
For a project plan activity duration and their relationship is given below:
Activity
Preceding Activity
Duration (days)
A
−
4
B
−
10
C
A
8
D
A
,
B
7
E
C
,
D
9
The duration of critical path is ____ days.
Q.
Figure below shows the network for a particular project which consists of four activities.
Normal time and crash time for each activity are given below:
A
c
t
i
v
i
t
y
N
o
r
m
a
l
t
i
m
e
(
d
a
y
s
)
C
r
a
s
h
t
i
m
e
(
d
a
y
s
)
1
−
2
3
2
2
−
3
4
2
2
−
4
5
4
3
−
4
7
5
The minimum time required for the completion of a project is ________
Q.
For a project the following data is given.
Activity
Duration
Earliest
Latest
(in days)
Start Time
Finish Time
1
−
2
2
0
11
1
−
3
7
0
7
1
−
4
8
0
11
2
−
5
3
2
14
3
−
5
6
7
14
3
−
6
10
7
17
3
−
7
4
7
16
3
−
7
4
7
16
4
−
6
6
8
17
5
−
7
2
13
16
7
−
8
6
15
22
The free float for activity 3-7 is____ (in days)
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Critical Path and Project Completion Time
OTHER
Watch in App
Explore more
Critical Path and Project Completion Time
Other Other
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app