A project consists of 7 activities with the following data.

ActivityPredecessorDuration (days)A4B3CA3DA5EB,C5FB,C6GD,E8

The minimum time required to complete the project (in days) is ____.

Open in App
Solution




PathDuration (days)ADG4+5+8=17ACEG4+3+5+8=20 (CP)BEG3+5+8=16BF3+6=9ACF4+3+6=13

Minimum time required to complete the project = 20 days.