wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A project following six activities

Activity Normal time(days) Normal cost(₹) time(days) cost(₹) Cost slope
1 - 2 4 1600 3 1800 200
1 - 3 9 2700 7 3500 400
2 - 3 3 1500 3 1500 0
3 - 4 6 2400 5 2800 400
3 - 5 7 4200 5 5000 400
4 -5 3 1800 2 2400 600

A
22300 and 14 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
22300 and 18 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
₹22150 and 15 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
₹22200 and 16 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C ₹22150 and 15 days

Critical path = 1 - 2 -3 - 4 - 5
Critical path duration = 9 + 6 + 3 = 18 days
Total cost = (1600 + 2700 + 1500 + 2400 + 4200 + 1800) + (18 x 450)
= ₹22300
We can crash activity along the critical path for reducing the project duration. Crashing activity 1 - 3 by two days.


Now there are two critcal paths.
1 - 2 - 3 -4 - 5 = 4 + 3 + 6 + 3 = 16 days
1- 3 - 4 - 5 = 7 + 6 + 3 = 16 days
Total cost after crashing = 1600 + 3500 +1500 + 2400 + 4200 + 1800 + (16 x 450)
= ₹22200
Crashing activity 3 - 4 by one more day.





Critical path = 1 - 2 - 3 - 4 - 5 = 4 + 3+ 5 +3 = 15 days
= 1 - 3 - 4 -5 = 7 + 5 + 3 = 15 days
Project cost = 1600 + 3500 + 1500 + 2800 + 4200 + 1800 + (15 x 450)
= ₹22150
For during critical path, activity 4-5 can be crashed by one day.


Critical path duration = 1 - 2 - 3 - 4 - 5 = 4 +3 + 5 + 2 = 14 days
1 - 3 - 5 Duration 14 days
1 - 2 - 3 - 4 - 5 Duration 14 days
1 -2 - 3 - 5 Duration 14 days
1- 3 - 4 - 5 Duration 14 days
Total project cost = 1600 + 3500 + 1500 + 2800 + 4200 + 2400 + (14 + 450)
= ₹22300
Crashed critical path duration = 14 days
Crash project cost = ₹22300
Ans: Project cost is minimum for 15 days. So optimum cost is ₹22150 and optimum project duration is 15 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Addition of Integers
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon