A project has activities A, B, C and D as shown below

Activity Normal
(days)
Cost Slope
(Rs/day)
A (1-2) 6 300
B (1-3) 8 100
C (2-3) 3 200
D (3-4) 4 500

The normal cost of the project is Rs. 4000 and the project overhead cost is Rs. 300 per day. If the project duration has to be crashed to 10 days the total project cost would be _______

A
7500
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7500
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8000
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
7900
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 7900
Activity Cost Slope
A 300
C 200
D 500
Crash 'C' by 1 day in stage 1
Stage 1:
Path Duration
A-C-D 12
B-D 12

Target is 10 days, hence we need to crash both the critical paths by 2 days

'A' by 1 day
'B' by 1 day
A-C-D path becomes 10 days

Path Duration
A-C-D 10
B-D 10

'B' by 2 days B - D

Total project cost for 10 days = Total normal cost + Crashing cost + Total indirect cost

=4000+200×2+300×2+100×2+300×1

'C' by 'A' by 'B' by
2 days 1 day 2 days

= 4000 + 900 + 3000 = 7900/-


flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Profit Maximisation
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon