A project has activities A, B, C and D as shown below
Activity | Normal (days) |
Cost Slope (Rs/day) |
A (1-2) | 6 | 300 |
B (1-3) | 8 | 100 |
C (2-3) | 3 | 200 |
D (3-4) | 4 | 500 |
Activity | Cost Slope |
A | 300 |
C | 200 |
D | 500 |
=4000+200×2+300×2+100×2+300×1
'C' by 'A' by 'B' by
2 days 1 day 2 days
= 4000 + 900 + 3000 = 7900/-