A project has seven activities, each with totally deterministic
completion time.

Activity Immediate
Predecessor
Normal
Time (days)
A - 9
B A 6
C A 7
D A 5
E B,C 4
F C,D 6
G E,F 7

The project completion time (days) and total float (days) on activity 'F' respectively are

A
29,0
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
26,0
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
29,2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
27,2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 29,0

Paths in Network
ABEG 9+6+4+7= 26
ACEG 9+7+4+7=27
ACFG 9+7+6+7=29 (Critical path)
ADFG 9+5+6+7 = 27


Total float on activity 'F' 22-16-6 =0

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Total, Average, and Marginal Product
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon