A project has seven activities, each with totally deterministic
completion time.
Activity | Immediate Predecessor |
Normal Time (days) |
A | - | 9 |
B | A | 6 |
C | A | 7 |
D | A | 5 |
E | B,C | 4 |
F | C,D | 6 |
G | E,F | 7 |
Paths in Network |
ABEG → 9+6+4+7= 26 |
ACEG → 9+7+4+7=27 |
ACFG → 9+7+6+7=29 → (Critical path) |
ADFG → 9+5+6+7 = 27 |