Question

A project manager estimates that a project will take x hours to complete, where x>100. The goal is for the estimate to be within 10 hours of the time it will actually take to complete the project. If the manager meets the goal and it takes y hours to complete the project, which of the following inequalities represents the relationship between the estimated time and the actual completion time?

A
x+y<10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
y>x+10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
10<yx<10
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
10yx10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 10<yx<10

Actual time for completing =y hours

Estimated time =x hours

Estimated time can be 10 hours greater or 10 hours lesser than actual time.

|xy|<10

Or |yx|<10

Hence 10<yx<10


flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon