Depth of ditch =3 m
Width of ditch =2 m
Length of ditch =12 m =0.5 m
∴ Volume of ditch
= Depth × Width × Length
=3 × 2 × 0.5
=3 cubic m
Hence, 3 cubic m sand is needed to fill the ditch.
∴ Cost of filling 1 cubic m sand
=Rs.10.50
∴ Cost of filling 3 cubic m sand
=Rs.10.50 × 3
=Rs.31.50
Thus the cost of filling sand is Rs. 31.50.