Question

A standard machine tool and an automatic machine tool are being compared for the production of a component. Following data refers to the two machines.

Standard Machine tool Automatic Machine tool
Setup time 30 min. 2 hours
Machining time per piece 22 min. 5 min
Machine rate Rs. 200 per hour Rs. 800 per hour

The breakeven production batch size above which the automatic machine tool will be economical to use, will be

A
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
24
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
225
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 225
Total cost of x1 component by using standard machine tool

(TC)1=(3060+22x160)×200

=100+220030 x1

Total cost x2 component by using an Automatic machine tool.

(TC)2=(2+560×x2)×800

=1600+200030 x2


Let the break even quantity be x.
At break even point

(TC)1=(TC)2

100+220030 x=1600+200030 x

6.667x=1500

x=225

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Addition of Fractions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon