A synchronous generator is connected to infinite bus through a loss-less line and a circuit breaker. The generator is delivering 1.0 p.u. power to infinite bus. The time of operation of CB is 0.1 sec. If the mechanical input to synchronous generator is suddenly increased to double, the time of operation of CB should be

A
0.1 second
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
more than 0.1 second but less than 0.2 seconds
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
does not depend on mechanical input
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
less than 0.1 second
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D less than 0.1 second
The maximum time of operation of CB is tc second,

tc=Criticaltime

tc=2H(δcrδ0)πf.Ps

tc1P

If P,tcso time of operation of CB should be less than 0.1 second

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Transformer
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon