wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?

A
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1 day
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 1 day
35 men completed the remaining job in 12 days.
Now the same job has to be done by 30 men.
We know that, M1D1=M2D2
Required time =35×1230=14 days
Delayed time =(1413)=1 day.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Direct Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon