A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
A
5days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1day
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D1day 35 men completed the remaining job in 12days. Now the same job has to be done by 30men. We know that, M1D1=M2D2 Required time =35×1230=14days Delayed time =(14−13)=1day.