Question

A work is done by 10 workers in 6 hours? How many workers will be required to do the same work in 4 hrs?

A
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
15
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!