Question

A work twice as fast as B. If both of them can together finish a piece of work in 12 days, Then B alone can do it in

A
24 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
27 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
36 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
48 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 36 days
Let us consider work done by B in 1 day =x
So, the work done by A in 1 day =2x

Now,
Number of days A and B together requires to complete a piece of work =12 days
Work done by both A and B together in 1 day =1/12

2x+x=1/12
3x=1/12
x=1/36

B can do work in 36 days

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon