wiz-icon
MyQuestionIcon
MyQuestionIcon
5
You visited us 5 times! Enjoying our articles? Unlock Full Access!
Question

A workforce of 210 men with a supervisor can finish a certain piece of work in 5 months. How many extra men must he employ if he want to complete job in just 2 months?
[2 marks]

Open in App
Solution


Let the extra men employed be x.
Number of men 210 x
Time (in months) 5 2

As number of men [M] will increase, the time duration [D] to finish a work will be less.
Hence, it is a case of inverse proportion.
MD=constant
M1D1=M2D2

[0.5 mark]

210×5=x×2
x=210×52=525

Therefore, the required number of men to finish the work in 2 months is 525 men, i.e. 315 extra men needed.

[1.5 marks]

flag
Suggest Corrections
thumbs-up
5
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Direct Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon