A workpiece of 2000mm length and 300mm width was machined by a planning operation with the feed set at 0.3mm/stroke. If the machine tool executes 10 double strokes/min, the planning time for a single pass will be
A
50min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
100min
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
200min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
220min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B100min Given data:
Workpiece length, l=2mm
Width, w=300mm
Feed =0.3mm/stroke
Number of strokes required (SN) =10double strokes/min SN=20strokes/min
Total machining time =LSN=200020(strokesmin)=100min