A workpiece of 2000mm length and 300mm width was machined by a planning operation with the feed set at 0.3mm/stroke. If the machine tool executes 10 double strokes/min, the planning time for a single pass will be

A
50min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
100min
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
200min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
220min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 100min
Given data:
Workpiece length, l=2mm
Width, w=300mm
Feed =0.3mm/stroke
Number of strokes required (SN)
=10double strokes/min
SN=20strokes/min
Total machining time
=LSN=200020(strokesmin)=100min

flag
Suggest Corrections
thumbs-up
1
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Planing and Slotting
PRODUCTION
Watch in App
Join BYJU'S Learning Program
CrossIcon