Abdul can paint a wall in 20 day. He starts work but has to stop it due to illness after 5 days. Rohan then completes the work in 12 days. How long would Rohan have taken to do the entire work by himself?

Open in App
Solution

Abdul can paint a wall in 20 days,

work done by Abdul in one day =120

work done by Abdul in 5 days = 120×5=14

Remaining part of work = 114=34

Rohan then completes the work in 12 days

work is done by Rohan in one day

=RemainingworkNo.ofdayshetooktocompletethework

=3412=116

work done by Rohan in one day = 116