After A has finished 12 of a piece of work in 10 days, B joins for 5 days. Later A completes the work which still remains in 4 more days. In how many days could B alone have done the complete work ?
A
12.22
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
16.66
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
18.66
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
19.33
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C16.66 After A has finished half of a job i.e. 50% of job in 10 days. Work rate of A=5010=5% per day Later, A completes the remaining work in 4 more days. It means A has completed 20% another work. So, B has done 30% of work in 6 days. Work rate of B=305=6% per day. Thus, B alone can complete whole work =1006=16.66 days.