Akhil has to lift a load of 800 N onto a platform of 2 m height. Instead, he pushes the load up a ramp 4 m long. Find the work done by Akhil in lifting the load vertically up.
A
800 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1600 J
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
400 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
200 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 1600 J The work done by Akhil in lifting the load vertically up = Force × height =800×2=1600J