Question

An automobile plant contracted to buy shock absorbers from two supplies X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X's shock absorbers, 96% are reliable. Of Y's shock absorbers, 72% are reliable.

The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y is

A

0.288
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

0.334
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

0.667
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

0.720
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B
0.334
Let total 100 shock absorbers are supplied

So X supplies = 60 (40% of 100)

Y supplies = 40 (60% of 100)

Reliable supply by X = 96% of 60 = 57.6

Reliable supply by Y = 72% of 40 = 28.8

So the required probability that random chosen reliable shock absorber is made by Y is

Required probability

=28.857.6+28.8

=0.334

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Probability
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon