Question

An engineer said be could finish a highway section in 3 days with his present supply of a certain type of machine. However, with 3 more of these machines the job could be done in 2 days. If the machines all work at the same rate, how many days would it take to do the job with one machine?

A
6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
18
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
E
36
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is D 18
suppose that the work done by each machine is X
and the total number of machine initially=Y
now, according to the quetion we have
3XY=1........(1)
2(XY+3Y)=1.........(2)
so from (1) and (2) we get
2(13+3X)=1

13+3X=12

3X=12-13

3X=16

X=118
so that the single machine will take 18 days to complete the work.
so option D is correct.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Cel & Mia at Wonderla
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon