The correct option is A supervisory costs
An example of a production overhead would be supervisory costs.
Materials and labour costs would be directly attributable to the product and would be classed as direct costs. Rent is a non production overhead but salaries of supervisors are related to production and are an overhead as they do not vary directly with output.