Anil, Bhuvan and Chandan take 10, 20, and 25 days to complete a job. What is the minimum time required to finish the job if not more than two of them work together on a single day and no two consecutive days have the same pair of people working?

A
6.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
61315 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
7.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
72128 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 61315 days
Assume total amount of work = 100 units.
A does = 10 units/day, B does = 5 units/day, and C does = 4 units/day
Possible Pairs:
A+B = 15 units/day, A+C = 14 units/day, B+C = 9 units/day
To minimize time, we will use the first two pairs.
So, 15 +14 +15 + 14 + 15 +14 + 15 = 102 units.
So, little less than 7 days are required
Hence, option (b) is correct answer.

flag
Suggest Corrections
thumbs-up
4
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon