Assume that only one client's order can be processed at any given point of time. So, Anish or Bani cannot start preparing a new order while a previous order is being prepared.
At what time is the order placed by Client 3 completely served?


A

10 : 35

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

10 : 22

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

10 : 25

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

10 : 17

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

10 : 25


For client 2’s order, it takes 5 minutes to serve completely beginning 10:10. Hence, the client 2 is completely served at 10:15. Now, coming to the client 3’s order of 1 burger and 1 portion of fries, it takes 10 minutes to serve burger while just 5 minutes to serve 1 portion of fries. Hence, he is completely served at 10:25.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
A+B+C=N (N Fixed), with Upper Limit
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon