Bangalore dairy sales Milk in two kinds of packets: Plastic Bag & Tetra Packs. Each of these packets goes through three steps: Filling, Sealing and Labelling. The company has three filling machines, 6 sealing machines and 3 labelling machines. Each of these 12 machines can work for exactly 8 hours in a day. One box of Tetra Packs requires 20 minutes for filling, 1 hour for sealing and 20 minutes for Labelling. The box of Plastic Bags requires 15 minutes for filling, 1 hour for sealing and 10 minutes for labelling. If the dairy has to manufacture only 40 boxes of Tetra Packs then how many machine hours are utilised on that day?

A
2 hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
66 2/3 hrs
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
30 hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
72 hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
40 hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 66 2/3 hrs

Each box of Tetra Pack takes 20 minutes for filling, 1 hour for sealing and 20 minutes for Labelling.

Total Machine Hours Utilised = 800 + 2400 + 800 = 4000 = 6623 hours.
Hence option (b)


flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon