Event numbersActivityDuration12A513B623C324D845Dummy035E236F1146H156G12

Red flagged activities are

Open in App
Solution




PathDurationADH5+8+1=14ADG5+8+12=25Critical pathACEG5+3+2+12=22ACF5+3+11=19BEG6+2+12=20BF6+11=17

Critical activities cannot be red flagged.

For red flagging

Free Float > Total Float

(They are essentially non critical activities)

ACTIVITY-B––––––––––––––

TF - LFT - EST - Duration

=1160=5

FF = TF - Head event slack

=5(118)=2

ACTIVITY-C––––––––––––––

TF = LFT - EST - Duration

=1153=3

FF = TF - Head event slack

=3(118)=0

For activities B & C

FF > TF hence they can red flagged .

flag