Question
Chaman is 50% more efficient than Aman. In how many days can Chaman alone complete the work if Aman and Chaman can complete the work together in 42 days.
A
70 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
60 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
65 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
55 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
85 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A 70 days Let the amount of work done by Aman alone in one day be x units.
So, the amount of work done by Chaman alone in one day = 1.5x
So, the total work = 42 × (x + 1.5x) = 105x
Time taken by Chaman to complete the work alone = 105x/1.5x = 70 days