Question

Chaman is 50% more efficient than Aman. In how many days can Chaman alone complete the work if Aman and Chaman can complete the work together in 42 days.

A
70 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
60 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
65 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
55 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
85 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 70 days
Let the amount of work done by Aman alone in one day be x units.

So, the amount of work done by Chaman alone in one day = 1.5x

So, the total work = 42 × (x + 1.5x) = 105x

Time taken by Chaman to complete the work alone = 105x/1.5x = 70 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Solving QE by Factorisation
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon