Question

Chase can do a job in 3hrs whereas Campbell can do the same job in 4hrs. If they work together, how long would it take them to finish the job?


Open in App
Solution

Solve for the required time:

Given that Chase can do a job in 3hrs whereas Campbell can do the same job in 4hrs.

Let the total work be L.C.M.3,4=12units

Work done by Chase in an hour =123=4units

Work done by Campbell in an hour =124=3units

Total work done by Chase and Campbell together in an hour =3+4=7units

Time taken by them to finish the job together =127=157hrs

Hence, it would take 157hrs to finish the job if they work together.