Choose the correct answer from the alternatives given. A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In how many days all the three together can do the work?
A
80 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
100 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
60 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
150 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 60 days Let the total unit of work be 360 units (LCM of 7; 120 & 90) (A + B) do = 36072 = 5 units/day (B + C) do = 360120 =3 units / day (C + A) do = 36090 4 units/day 2(A + B + C)s per day work =5+3+4=12 units. (A + B + C)s per day work =6 units Time taken by (A + B + C) together to complete the work =3606 = 60 days.