Consider a PERT network for a project involving six tasks (a to f)
Task | Predecessor | Expected task time (in days) | Variance of the task time (in days2) |
a | - | 30 | 25 |
b | a | 40 | 64 |
c | a | 60 | 81 |
d | b | 25 | 9 |
e | b, c | 45 | 36 |
f | d, e | 20 | 9 |
Task | Variance (σ2) |
a | 25 |
c | 81 |
e | 36 |
f | 09 |