Question

Consider a PERT network for a project involving six tasks (a to f)

Task Predecessor Expected task time (in days) Variance of the task time (in days2)
a - 30 25
b a 40 64
c a 60 81
d b 25 9
e b, c 45 36
f d, e 20 9

The standard deviation of the critical path of the project is

A
155 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
151 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
200 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
238 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 151 days
For critical path a-c-e-f, the variance for each task is shown below
Task Variance (σ2)
a 25
c 81
e 36
f 09


Total variance = 25 + 81 + 36 + 9 = 151

We know that

Standard deviation,

σ=Variance

S.D. of critical path,

σcp=151 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Passage 10
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon