Question

Consider a pipeline which takes 7 cycles to executes 1st instruction. the same task can be completed in a non - pipelined system with x cycles. For 994 instruction the speed up of pipeline is 4.97 as compared to the non-pipeline system. The value of x is __________.

Open in App
Solution

option (c)

Number of cycles needed to complete 1st instruction in pipeline

= number of segments (k)

= 7

k = 7

pipeline time = k + n - 1 = 7 + 994 - 1 = 1000

non-pipeline time = 994 * x

Speed up=994x1000

4.97=994x1000

x = 5