wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Consider following table showing the max demand of each process & currently allocated resources to the process. There are total 15 resources. Which of the following is not safe sequence?
ProcessMaximum DemandCurrent AllocationP152P221P371P4105P5123

Open in App
Solution


Available : 15 -12 = 3


flag
Suggest Corrections
thumbs-up
1
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Banker's Algorithm
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon