Consider following table showing the max demand of each process & currently allocated resources to the process. There are total 15 resources. Which of the following is not safe sequence?
ProcessMaximum DemandCurrent AllocationP152P221P371P4105P5123

Open in App
Solution


Available : 15 -12 = 3