Consider the following activities from A to J

ActivityPredecessorDuration (month)A-2BA6C A4DA2ED5FD6GE4HF,G1IC,H3JB3

The free float activity J is.
  1. 6

Open in App
Solution

The correct option is A 6


Critical Path ADEGHI

Activity J :

Free Float =TjETiEtij

=(178)3
=6