Consider the following measuring structures:
1. Submerged broad-crested weir
2. Free broad-crested weir
3. Free sharp-crested weir
4. Free ogee spillway
The correct sequence of the increasing order of the discharge coefficient of these structures is
H1/Bw≤0.1 Long crested weir
01<H1/Bw<0.35 Broad−crested weir
0.35≤H1/Bw<1.5 Narrow−crested weir
H1/Bw≥1.5 Sharp-crested weir
Further submerged weirs have lesser coefficient of discharge compared to free weirs. So 2 will come after 1.