Consider the following network of activities, with each activity named A-L, illustrated in the nodes of the network
The number of hours required for each activity is shown alongside the nodes. The slack on the activity L, is ____ hours.
Open in App
Solution
The correct option is
A
2
Time along path A - B - C - F - I - J - K = 42 hours
Time along path A - B - C - E - H - L = 31 hours
Time along path A - B - C - D - G - H - L = 40 hours
Slack for L = 42 - 40 = 2 hours
Suggest Corrections
0
Similar questions
Q.
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is
Q.
Find time spent by a child during
24
hours is shown in the pie child in each activity.
Q.
The network diagram for a project is shown below. The duration of activities is indicated.
The free float for activity 3 - 4 is
Q.
A human body required the 0.01 Curie activity of radioactive substance after 24 hours. A half-life of radioactive is 6 hours. The activity of the radioactive substance that can be injected will be:
Q.
The activity of a sample reduces from
A
0
to
A
0
√
3
in one hour. The activity after
3
hours more will be
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Probability Distribution
MATHEMATICS
Watch in App
Explore more
Probability Distribution
Standard XII Mathematics
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app