CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Consider the following PERT network:



The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:

Activity Optimistic time (days) Most likely time (days) Pessimistic time (days)
1 - 2 1 2 3
1 - 3 5 6 7
1 - 4 3 5 7
2 - 5 5 7 9
3 - 5 2 4 6
5 - 6 4 5 6
4 - 7 4 6 8
6 - 7 2 3 4

The critical path duration of the network (in days) is

A
11
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
14
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
18
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
17
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 18
Activities Duration te=to+4tm+tp6 EST LST EFT LFT LST - EST = Float Variance σ2 (tpto6)2
1 - 2 1+4×2+36=2 0 0 2 3 0 (316)2=436
1 - 3 5+6×4+76=6 0 0 6 6 0 (756)2=436
1 - 4 3+4×5+76=5 0 0 5 12 7 (736)2=1636
2 - 5 5+4×7+96=7 2 3 10 10 1 (956)2=1636
3 - 5 2+4×4+66=4 6 6 10 10 0 (626)2=1636
5 - 6 4+4×5+66=5 10 10 15 15 0 (646)2=436
4 - 7 4+4×6+86=6 5 12 18 18 7 (846)2=1636
6 - 7 2+4×3+46=3 15 15 18 18 0 (426)2=436


Critical path =13567
(Marked by double lines)

Critical path duration of the network = 6 + 4 + 5 + 3 = 18 days

flag
Suggest Corrections
thumbs-up
5
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Mean Deviation about Mean for Discrete Frequency Distributions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon