Consider the following PERT network:
The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:
Activity | Optimistic time (days) | Most likely time (days) | Pessimistic time (days) |
1 - 2 | 1 | 2 | 3 |
1 - 3 | 5 | 6 | 7 |
1 - 4 | 3 | 5 | 7 |
2 - 5 | 5 | 7 | 9 |
3 - 5 | 2 | 4 | 6 |
5 - 6 | 4 | 5 | 6 |
4 - 7 | 4 | 6 | 8 |
6 - 7 | 2 | 3 | 4 |
Activities | Duration te=to+4tm+tp6 | EST | LST | EFT | LFT | LST - EST = Float | Variance σ2 (tp−to6)2 |
1 - 2 | 1+4×2+36=2 | 0 | 0 | 2 | 3 | 0 | (3−16)2=436 |
1 - 3 | 5+6×4+76=6 | 0 | 0 | 6 | 6 | 0 | (7−56)2=436 |
1 - 4 | 3+4×5+76=5 | 0 | 0 | 5 | 12 | 7 | (7−36)2=1636 |
2 - 5 | 5+4×7+96=7 | 2 | 3 | 10 | 10 | 1 | (9−56)2=1636 |
3 - 5 | 2+4×4+66=4 | 6 | 6 | 10 | 10 | 0 | (6−26)2=1636 |
5 - 6 | 4+4×5+66=5 | 10 | 10 | 15 | 15 | 0 | (6−46)2=436 |
4 - 7 | 4+4×6+86=6 | 5 | 12 | 18 | 18 | 7 | (8−46)2=1636 |
6 - 7 | 2+4×3+46=3 | 15 | 15 | 18 | 18 | 0 | (4−26)2=436 |