Consider the following PERT network:
The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:
Activity | Optimistic time (days) | Most likely time (days) | Pessimistic time (days) |
1 - 2 | 1 | 2 | 3 |
1 - 3 | 5 | 6 | 7 |
1 - 4 | 3 | 5 | 7 |
2 - 5 | 5 | 7 | 9 |
3 - 5 | 2 | 4 | 6 |
5 - 6 | 4 | 5 | 6 |
4 - 7 | 4 | 6 | 8 |
6 - 7 | 2 | 3 | 4 |