wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Consider the following PERT network:


The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:

Activity Optimistic time (days) Most likely time (days) Pessimistic time (days)
1 - 2 1 2 3
1 - 3 5 6 7
1 - 4 3 5 7
2 - 5 5 7 9
3 - 5 2 4 6
5 - 6 4 5 6
4 - 7 4 6 8
6 - 7 2 3 4

The standard deviation of the critical path is

A
0.33
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1.66
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
0.55
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0.88
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Join BYJU'S Learning Program
CrossIcon