Consider the following statements:
1. Only a one-time estimate is required for each activity.
2. Project is analyzed based on normal probability distribution.
3. Float determines the time by which activity can be delayed without delaying the scheduled project duration.
4. It is an event-oriented diagram
Which of the above statements are correctly applied to the PERT network?