Consider the following statements regarding "Slack".
I. "Slack" is the difference between the latest allowable occurance time and earliest expected occurrence time of an activity of a project.
II. The critical path connects the initial event with the end event through the events having zero or minimum "Slack" times.
Which of the above statements is/are correct ?