Consider the following statements with respect to PERT and CPM
1. PERT is a probabilistic approach and it is well suited for R&D
2. Project crashing is possible in a PERT network if cost elements are provided.
3. Critical path duration will be the minimum time required to complete the project in a CPM network.
Which of the above statements is/are correct?