Question
Convert the given AON network to that of AOA network
Legend [4, 1]
⇒
[Total estimate, variance],
Z = 1.65 for P(Z) = 0.95
The maximum completion time of project is
Open in App
Solution
Paths
Duration
a
−
d
−
g
4
+
4
+
6
=
14
a
−
c
−
e
−
g
4
+
5
+
6
+
6
+
21
→
C
P
a
−
c
−
f
4
+
5
+
1
=
10
b
−
e
−
g
2
+
6
+
6
=
14
b
−
f
2
+
1
=
3
T
e
=
21
(
Var
)
c
p
=
(
Var
)
a
+
(
Var
)
c
+
(
Var
)
e
+
(
Var
)
g
=
1
+
1
+
0.44
+
1
=
3.44
σ
c
p
=
√
3.44
=
1.854
Maximum completion time
=
T
e
+
3
σ
c
p
=
21
+
3
×
1.854
=
27
Suggest Corrections
0
Similar questions
Q.
Convert the given AON network to that of AOA network
95% probability of completing the project is
Q.
Convert the given AON network to that of AOA network
The number of dummies in the new network are
Q.
Assertion (A):
Linked bar chart cannot be developed from an AON network as easily as from an AOA network.
Reason (R):
AON network do not incorporate information corresponding to dummy arrows of AOA networks
Q.
Consider a PERT network for a project involving six tasks (a to f)
Task
Predecessor
Expected task time (in days)
Variance of the task time (in days
2
)
a
-
30
25
b
a
40
64
c
a
60
81
d
b
25
9
e
b, c
45
36
f
d, e
20
9
The expected completion time of the project is
Q.
The total number of errors in the given AOA network is _
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Time Estimates and Expected Time of an Activity
OTHER
Watch in App
Explore more
Time Estimates and Expected Time of an Activity
Other Other
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app