Convert the given AON network to that of AOA network



Legend [4, 1] [Total estimate, variance],
Z = 1.65 for P(Z) = 0.95

The maximum completion time of project is

Open in App
Solution

PathsDurationadg4+4+6=14aceg4+5+6+6+21CPacf4+5+1=10beg2+6+6=14bf2+1=3

Te=21

(Var)cp=(Var)a+(Var)c+(Var)e+(Var)g

=1+1+0.44+1=3.44

σcp=3.44=1.854

Maximum completion time =Te+3σcp =21+3×1.854=27