Less than earliest event time of the following node
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Less than or equal to earliest event time of the following node
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
Greater than earliest event time of the following node
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Greater than or equal to earliest event time of the following node
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B Less than or equal to earliest event time of the following node Earliest finish time of an activity is awalys less than or equal to earliest event time f the following node.