wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Efficiency of A is 33.33% more than that of B. B takes 24 days complete a work. How many days A will take to complete the work?

A
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
25
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
18
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
16
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
14
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 18

Efficiency x time = work( constant)

Efficiency of A is 33.33% () more. So time taken by A will be 25 % less than that by B => A will take 18 days.

Alternatively: -

Let the work done by B in a day = 33 units

The same work is done by A in a day = 44 units

Work done by B in 24 days = 33 x 24 units

The same work is done by A = 33 x 24/ 44 = 18 days


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Averages and Alligations Concepts
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon