The correct option is D 10 hours
Initial setting time of cement should be more than 45 mins. This is to allow enough time for transportation and placing of concrete before setting starts. Final setting time should be less than 375 minutes. 375 minutes is equivalent to 10.25 hours. Hence, the final setting time of cement should not be more than 10 hours.