Question

Find the cost of digging a cubodial pit 8 m long, 6 m broad and 3 m deep at the rate of Rs 30 per m3.

Open in App
Solution

Length of pit (l) = 8 m

Width (b) = 6 m

and depth (h) = 3 m

Volume of earth dug out = lbh

=8×6×3=144 m3

Cost of digging the pit at the rate of Rs 30 per m3

=144×30=Rs 4320